Cleanroom Construction Control Regulations

  • Author:Jason Peng

  • Cleanroom Engineering Technology Manager of Deiiang Company.

    Product R&D Manager of GDC Inc. Cleanroom Equipment Manufacturing Company.

    Executive Director of Guangdong Cleanroom Industry Association of China.

    Engaged in R&D of related products for 15 years, with rich relevant technical experience

  • 2024-12-02  |  Visits:
Clean room construction Management Protocol

Regulations for maintaining cleanliness and safety during clean room construction

During the construction of the clean room, there are many Manufacturers and workers. In order to effectively manage and avoid confusion, each construction unit must provide clean clothes, shoes and hats with their own unit logo.

General Rules

In addition to these control regulations, general safety and hygiene regulations for safe and civilized construction must be observed.

Scope of Application

Within the clean room area

Control Time

During the construction of the clean room.

Access Control

Control personnel in and out, and require personnel to register personnel and construction cleaning tools and materials before entering the clean room.

Cleanroom Construction in your Existing Structure - Angstrom Tech

Clean room construction

Preparation Before Construction

1.Anyone entering must fill out an application form. One project requires one application form, valid for max one week.
2.Construction permits must be worn when entering the clean control area.
3.Prepare vacuum cleaners and other necessary cleaning tools.
4.All tools and materials must be wiped clean before entering the clean area.
5.Non-essential items like food and drinks are prohibited.
6.Everyone must enter and exit through designated entrances.
7.Clean clothing should be worn at all times.
8.Construction machinery must have contractor logos.
9."Hot work" requires special application submission.

Cleanroom Maintenance Checklist - Lighthouse Worldwide Solutions

Clean room maintenance

Precautions During Construction

1

No smoking, eating, or betel nuts in clean areas

2

No oil usage; tools must not leak oil

3

Use clean aluminum samples and scaffolding only

4

Transport materials off ground without dragging

5

Only trucks with rubber wheels permitted

6

Protect surroundings when welding is necessary

7

Isolate work areas with plastic sheets for pollution work

8

Mark any dangerous situations at the construction site

Cleanroom Processes and Equipment performance management, an interview with José Rodrigues - Facility Manager - INL

Clean room personnel management

9

Wear work permits at all times

10

Follow instructions from owner and responsible engineers

11

Follow electricity safety regulations when using power

12

Dispose of flammable materials immediately

13

Report any damage to equipment/pipelines immediately

14

Wear safety helmets; safety belts for overhead operations

15

Install protective boards above Clean room ceiling

16

5:1 manager-to-worker ratio for ceiling work

Clean Room Construction Management Protocol | Document Version 1.0