How long does it take to build a clean room?

  • Author:Jason Peng

  • Cleanroom Engineering Technology Manager of Deiiang Company.

    Product R&D Manager of GDC Inc. Cleanroom Equipment Manufacturing Company.

    Executive Director of Guangdong Cleanroom Industry Association of China.

    Engaged in R&D of related products for 15 years, with rich relevant technical experience

  • 2024-11-06  |  Visits:

The construction time of A Clean Room is affected by many factors, including area, structure type, international logistics, and the construction period of sub-projects. These factors will be analyzed in detail below.

cleanroom-construction.jpg

Relationship with area

The area of the clean room directly affects the construction time. Generally speaking, the larger the area, the longer the construction time required. Taking a 100 square meter clean room as an example, the construction time may be between 3-6 months, while a 500 square meter modular clean room may take 6-12 months. The increase in area not only increases the use of materials, but also requires more manpower and time for construction.

  • 100 square meters: 3-6 months

  • 500 square meters: 6-12 months

Related to the type of clean room structure

Different types of clean room structures will affect the construction time.cleanroom_const20_1_large-1.jpg

1. Hard wall clean room

Hard wall clean rooms usually use concrete or metal materials, and the construction period is longer, usually 3-6 months, because their structure is stable and requires high construction precision.

2. Soft-wall cleanroom

Soft-wall cleanrooms use lightweight materials and are relatively simple to construct, usually taking 2-4 months, suitable for quick construction and disassembly.

3. Modular cleanroom

Modular cleanrooms use prefabricated modules, with the shortest construction time, usually completed within 1-3 months, suitable for rapid response to market demand.

  • Hard wall: 3-6 months

  • Soft wall: 2-4 months

  • Modular: 1-3 months

International logistics

The efficiency of international logistics directly affects the material supply for modular cleanroom construction. If the materials are imported from abroad, it usually takes 1-2 months for transportation and customs clearance. Logistics delays may lead to delays in the overall construction progress, so choosing a local supplier can effectively shorten the construction time.

Construction period of sub-projects

The construction time of each sub-project should also be considered:Cleanroom-Construction2.jpg

1. Wall partition ceiling

generally 1 month, 2-3 months for large areas.

2. Ventilation duct project

generally 1 month, 2-3 months for large areas.

3. Purification air conditioning unit

production cycle is about 30 days.

4. Ground construction

20-30 days.

5. Equipment installation and commissioning

10-20 days.

-  of sub-projects:

  • Wall partition: 1-3 months

  • Ventilation duct: 1-3 months

  • Purification air conditioning unit: 30 days

  • Ground construction: 20-30 days

  • Equipment installation and commissioning: 10-20 days

a-cleanroom-construction1.jpg

the time to build a clean room varies depending on many factors, usually between 3 and 12 months. Choosing the right structure type and material supplier, and arranging the construction period reasonably can effectively shorten the construction time.