The construction time of A Clean Room is affected by
many factors, including area, structure type, international logistics, and the
construction period of sub-projects. These factors will be analyzed in detail
below.
Relationship with area
The area of the clean room directly affects the construction time. Generally speaking, the larger the area, the longer the construction time required. Taking a 100 square meter clean room as an example, the construction time may be between 3-6 months, while a 500 square meter modular clean room may take 6-12 months. The increase in area not only increases the use of materials, but also requires more manpower and time for construction.
100 square meters: 3-6 months
500 square meters: 6-12 months
Related to the type of clean room structure
Different types of clean room structures will affect
the construction time.
1. Hard wall clean room
Hard wall clean rooms usually use concrete or metal materials, and the construction period is longer, usually 3-6 months, because their structure is stable and requires high construction precision.
2. Soft-wall cleanroom
Soft-wall cleanrooms use lightweight materials and are relatively simple to construct, usually taking 2-4 months, suitable for quick construction and disassembly.
3. Modular cleanroom
Modular cleanrooms use prefabricated modules, with the shortest construction time, usually completed within 1-3 months, suitable for rapid response to market demand.
Hard wall: 3-6 months
Soft wall: 2-4 months
Modular: 1-3 months
International logistics
The efficiency of international logistics directly affects the material supply for modular cleanroom construction. If the materials are imported from abroad, it usually takes 1-2 months for transportation and customs clearance. Logistics delays may lead to delays in the overall construction progress, so choosing a local supplier can effectively shorten the construction time.
Construction period of sub-projects
The construction time of each sub-project should also
be considered:
1. Wall partition ceiling
generally 1 month, 2-3 months for large areas.
2. Ventilation duct project
generally 1 month, 2-3 months for large areas.
3. Purification air conditioning unit
production cycle is about 30 days.
4. Ground construction
20-30 days.
5. Equipment installation and commissioning
10-20 days.
- of sub-projects:
Wall partition: 1-3 months
Ventilation duct: 1-3 months
Purification air conditioning unit: 30 days
Ground construction: 20-30 days
Equipment installation and commissioning: 10-20 days
the time to build a clean room varies depending on many factors, usually between 3 and 12 months. Choosing the right structure type and material supplier, and arranging the construction period reasonably can effectively shorten the construction time.